In February 2022, InGauge Energy was contracted to plan and execute drilling operations on Wellesley 2, an exploration gas well in Queensland. Easternwell Rig 101 was mobilised after civils operations were completed. The well was drilled in just over 12 days from spud to rig release. All operational evaluation objectives were successfully completed, including multiple electric line logging operations and a drill stem test. The well was decommissioned on the 12th of February. Minimal downtime (<4%) was recorded throughout the execution phase of operations.

 inGauge looks forward to continue our next project with Lakes Blue Energy later in 2022.

Glenaras Pilot Enhancement Programme

Glenaras Pilot Enhancement Programme

inGauge provided engineering and project execution for the 2021 workover campaign aimed at enhancing production from the Glenaras Lateral Pilot area. The programme has now been completed and is showing signs of success with gas rates in the field increasing to near 80 Mscfd.